Targeting Stories for a Release

During release planning, product owners and managers review the Backlog and choose which Stories need to be included in the Release. The progress data for the Stories will be used to calculate the Release Progress and Release Burnup charts in the TRACKING Perspective.

  1. From the PLANNING perspective, select the Story you want to target for a Release.
  2. Click GUID-E5A11DAB-2D51-4C04-AAC0-B849DE1767C3-low.png > Assign to Release. The Assign to Release dialog box opens.
  3. Select a Release from the list and click OK.
Tip: To change multiple rows simultaneously:
  1. Show the Release column in the grid.
  2. Select multiple rows.
  3. Double click any Release cell and select the new value.
  4. Click Save.